When Is a Pre-Start Health and Safety Review Required?

Posted by  On June 16, 2022
Ontario Regulation 851 (the Industrial Establishments Regulation)

A Pre-Start Health and Safety Review (PSR/PHSR) is required in an Ontario factory when a new or modified apparatus, structure, protective element, or process falls within one of the eight circumstances in Section 7 of Ontario Regulation 851 and no Table exemption applies. Not every installation or modification requires a PSR.

HITE Engineering helps industrial facilities assess PSR requirements, identify safety deficiencies, and address compliance concerns.

Quick PSR/PHSR Applicability Checklist

If you’re unsure when a PSR is required in Ontario, start by reviewing the following questions.

  • Is your workplace considered a factory under Ontario’s Occupational Health and Safety Act? This can include manufacturing facilities, warehouses, and certain maintenance or processing operations.
  • Are you installing new equipment or machinery? New equipment may require a PSR if it falls within a Section 7 trigger category.
  • Are you modifying existing equipment or processes? Modifications may trigger a PSR when new or modified engineering controls or other measures are needed to comply with the applicable provisions in the Section 7 Table.
  • Are you installing or modifying machine guarding? Certain devices that signal a machine to stop and interlocking barrier guards fall within Item 2; fixed barrier guards alone do not automatically trigger a PSR.
  • Are you installing storage racks, lifting equipment, or dust collection systems? These systems may require a PSR where the specific Table circumstances apply and no documented exemption is available. Separate engineering obligations may also apply.
  • Does your process involve flammable liquids, combustible dust, or ignition hazards? Certain storage, dispensing, and processes with imminent ignition or explosion hazards are covered. Some hazardous-agent processes using exposure-control ventilation may also trigger a PSR.
  • Does a documented exemption apply? Some installations qualify for exemptions only where the specific conditions in the current Section 7 Table are satisfied and supporting records are available.

Answering yes to one or more questions does not automatically mean a PSR is required. The specific equipment, process, applicable regulatory provisions, and available exemption documentation must be considered.

The Ontario government’s PSR guideline provides additional information about these requirements.

The Main PSR/PHSR Trigger Scenarios

The Section 7 Table in Ontario Regulation 851 identifies eight circumstances that may require a PSR. The following article headings retain their original order for ease of reference; each description identifies the corresponding regulatory Table item and its relevant exemption.

1. Machine Guarding and Protective Elements

Item 2 covers safeguarding devices that signal an apparatus to stop, including safety light curtains, safety mats, area scanners, and two-hand controls, as well as barrier guards using mechanical or electrical interlocks. Fixed guards alone do not automatically trigger Item 2. A documented exemption may apply where the apparatus and protective elements meet the Table’s standards and installation conditions. HITE’s machine guarding engineering services help assess protective elements and applicable safety requirements.

2. Storage Racking and Stacking Structures

Item 3 addresses materials stored on industrial racks or stacking structures. New or modified installations may require a storage racking PSR to assess structural adequacy and the applicable requirements of clause 45(b). An exemption may apply where the structure is designed and tested in accordance with current applicable standards, with supporting documentation available. Routine rack inspections and damage assessments are separate from a statutory PSR.

3. Dust Collectors and Combustible Dust

Item 5 applies where a dust collector’s use creates a risk of ignition or explosion that presents an imminent hazard to a person’s health or safety. A dust collector PSR addresses the applicable requirements of section 65. The Section 7 Table provides no specific exemption for Item 5, but applicability depends on the actual process and hazard conditions.

4. Lifting Devices

Item 7 covers specified travelling, overhead, monorail, gantry and jib cranes, other structurally supported lifting devices, and vehicle lifts or hoists. A lifting device PSR may be required for a qualifying installation or modification. An exemption may apply where the supporting structure was originally designed for the lifting device being installed or used, or where a vehicle lift or hoist is certified to current applicable standards. Separate lifting-equipment compliance obligations may still apply.

5. Processes With a Risk of Ignition or Explosion

Item 4 applies when a process presents a risk of ignition or explosion creating a condition of imminent hazard to a person’s health or safety. A risk of ignition or explosion PSR addresses the applicable requirements of section 63. An exemption may apply to a process conducted inside a spray booth manufactured and installed in accordance with current applicable standards; equipment installed inside the booth may still trigger another PSR item.

6. Flammable Liquid Storage and Dispensing

Item 1 applies where more than 235 litres of flammable liquids are located in a building or room, or flammable liquids are dispensed in a building, room or area. A flammable liquid storage PSR may be required. The storage exemption requires no more than 235 litres per adequate cabinet, no more than three cabinets per group, and at least 30 metres between groups. There is no Item 1 exemption for dispensing flammable liquids.

7. Foundry Operations and Molten Materials

Item 6 applies where a factory produces aluminum or steel, or is a foundry that melts or handles molten material. A required PSR examines the specific molten-material provisions listed in the Section 7 Table. No Item 6 exemption is provided in that Table.

8. Hazardous Biological or Chemical Agents

Item 8 applies when a process uses or produces a hazardous biological or chemical agent and uses a ventilation system to limit worker exposure in accordance with the exposure limits in Regulation 833. The review addresses sections 127 and 128 of Regulation 851. The Table exempts certain portable extraction devices that do not exhaust outdoors. An appropriately qualified engineer or other permitted specialist may conduct an Item 8 review.

Examples of Situations That May Require a PSR/PHSR

Understanding when a PHSR is required can help facilities identify potential compliance obligations. The following examples highlight situations where a Pre-Start Health and Safety Review may be necessary.

  • Installing a new production line: A manufacturer introduces machinery with safety light curtains and interlocking guards that may fall under Section 7.
  • Expanding warehouse storage: A distribution facility installs new pallet racking and needs to determine whether a storage racking PSR or documented exemption applies.
  • Adding a dust collection system: A woodworking or food-processing facility installs a dust collector whose use could create an imminent ignition or explosion hazard.
  • Installing an overhead crane: A manufacturer adds a crane supported by a building structure and must confirm whether the supporting-structure exemption applies.
  • Changing a chemical process: A facility introduces a process presenting an imminent ignition or explosion hazard, or adds exposure-control ventilation for a hazardous biological or chemical agent.
  • Expanding flammable liquid storage: A plant increases its flammable-liquid inventory above 235 litres in a building or room or introduces dispensing, requiring an assessment of the relevant PSR trigger and any storage exemption.

These examples are not automatic PSR determinations. Each situation requires consideration of the specific equipment, workplace conditions, applicable regulations, and potential exemptions.

What a PSR/PHSR Is Not

A Pre-Start Health and Safety Review serves a specific regulatory purpose. It should not be confused with other workplace safety assessments.

A PSR is not simply a general safety checklist. It is a formal review of specified equipment, structures, protective elements, or processes against the applicable provisions in the Section 7 Table. It is not a general certification that equipment is safe for every use.

A PSR does not replace other compliance obligations. Employers remain responsible for meeting applicable requirements under the Occupational Health and Safety Act and other relevant regulations.

A PSR is not always the same as a risk assessment. A risk assessment can support a PSR, particularly for safeguarding and safety-control systems, but does not by itself replace the prescribed review and written report.

A PSR is not automatically required for like-for-like maintenance or repair. Modifications and relocations must be evaluated against the Section 7 circumstances; a move within the same workplace without relevant changes may not trigger another review.

What Information Should You Gather Before Contacting an Engineer?

Preparing the right information can help an engineer understand your equipment, identify potential PSR triggers, and establish the appropriate review scope.

A practical PHSR checklist for Ontario facilities includes:

  • Equipment drawings: Layouts, mechanical and structural drawings, electrical schematics, safeguarding layouts, or other available design information.
  • Photographs: Images of the equipment, installation area, protective elements, and surrounding conditions.
  • Process description: An explanation of how the equipment or process operates and how workers interact with it.
  • Equipment specifications: Manufacturer information, operating parameters, capacities, and available manuals.
  • Installation or modification details: Information about new equipment, planned changes, or modifications to existing systems.
  • Facility information: Site location, workplace type, and relevant operating conditions.
  • Known hazards: Identified machine guarding, lifting, combustible dust, chemical, or other safety concerns.
  • Project timeline: Planned installation, commissioning, startup, or production dates.

Existing engineering reports, risk assessments, previous PSR documentation, and documents establishing regulatory exemptions may also be useful.

How HITE Engineering Can Help

HITE Engineering provides Pre-Start Health and Safety Review services to help Ontario industrial facilities determine PSR requirements and address applicable engineering and safety obligations.

Depending on the project, our engineers can assist with:

  • Reviewing equipment and process information
  • Assessing potential Section 7 PSR triggers
  • Reviewing available exemption documentation
  • Completing applicable engineering assessments
  • Identifying deficiencies and required compliance measures
  • Preparing PSR/PHSR reports
  • Recommending appropriate corrective actions or follow-up engineering

With experience supporting Ontario workplaces since 1997, HITE helps facility managers, manufacturers, and health and safety teams address regulatory requirements through practical engineering review and documentation.

FAQs

Can HITE tell us if a PSR is required?

Yes. HITE can review equipment, process, and facility information to assess whether the circumstances in Section 7 of Ontario Regulation 851 apply and whether an exemption can be established.

The applicability assessment considers the relevant Table items, the nature of new installations or modifications, and supporting exemption documentation. It is separate from a formal PSR.

Who can perform a PSR/PHSR in Ontario?

Under subsection 7(4)(a) of Ontario Regulation 851, PSRs for Items 1 through 7 must be conducted by an engineer authorized to practise in Ontario.

Under subsection 7(4)(b), Item 8 may be reviewed by an engineer or another person with appropriate special, expert, or professional knowledge or qualifications, as permitted by the regulation.

How long does a PSR take?

The timeline depends on the equipment or process complexity, available documentation, inspection requirements, and the engineering analysis involved.

Providing drawings, specifications, photographs, and project deadlines can help establish the expected scope and schedule.

How much does a PSR cost?

PSR costs vary depending on the type of equipment, number of systems, engineering complexity, site requirements, and documentation available.

HITE can review the project information and discuss the appropriate scope before providing a proposal.

Can a PSR be completed after equipment is installed?

Yes. A required PSR may be completed after equipment is installed, but it must be completed before the equipment or process is operated or used, including applicable testing and commissioning, unless a valid Table exemption applies.

If equipment is already operating without a required pre-start review, the facility should obtain appropriate guidance to address its compliance obligations. A later assessment does not retroactively meet the pre-start requirement.

What happens if a PSR identifies deficiencies?

A PSR report identifies measures necessary for compliance with the applicable provisions and, where relevant, precautions before testing and details of structural adequacy for Items 3 and 7. The report must meet the signature, date, and engineering-seal requirements of Section 7.

Before the equipment or process is used, the required measures must be implemented or alternative measures achieving compliance must be documented through the written-notification process in subsection 7(6). Written notice does not permit non-compliant operation. The report must be provided to the joint health and safety committee or representative, if any, before use, and the required records must remain accessible at the workplace.

HITE can provide recommendations and follow-up engineering support where deficiencies require corrective action.

Determine Whether Your Facility Requires a PSR/PHSR

If you’re installing new equipment, modifying an industrial process, or reviewing existing safety systems, HITE Engineering can help assess whether a Pre-Start Health and Safety Review is required.

Contact us with your equipment details, available drawings, project location, and expected timeline to discuss your PSR/PHSR requirements.